Australia’s Gorgon LNG train to be out for five weeks

From argusmedia.com

One of three trains at Australia's 15.6mn t/yr Gorgon export terminal will be off line for five weeks, operator Chevron told Argus on 7 May. The train has been off line since 30 April because of a mechanical fault in a turbine. Chevron's five-week shutdown expectation is slightly longer than the initially expected shutdown period of about 2-3 weeks, traders said. Each week of downtime on one train at Gorgon reduces the terminal's available liquefaction capacity by about 100,000t. The five-week shutdown is likely to reduce the terminal's production by about 5-8 cargoes, traders said. One standard-sized cargo is ... (full story)